G&G Mech. Constructors, Inc. v. Jeff City Indus., Inc., 549 S.W.3d 492 (2018)

March 20, 2018 · Missouri Court of Appeals, Western District · WD 80840
549 S.W.3d 492

G&G MECHANICAL CONSTRUCTORS, INC., Respondent,
v.
JEFF CITY INDUSTRY, INC., a/k/a JC Industries, Inc. and Liberty Mutual Insurance Company, Appellants.

WD 80840

Missouri Court of Appeals, Western District.

Opinion filed: March 20, 2018

Jonathan Sternberg, Kansas City, for Respondent.

John A. Watt, Kansas City, for Appellant.

Before Division Three: Gary D. Witt, Presiding Judge, Lisa White Hardwick, Judge, and Edward R. Ardini, Jr., Judge

EDWARD R. ARDINI, JR., JUDGE

Jeff City Industry, Inc. ("JCI") entered into an agreement with the City of Columbia, Missouri, to serve as general contractor on the Hominy Trail Water and Sewer Project. JCI subcontracted certain boring work related to the project to G&G Mechanical Constructors, Inc. ("G&G"). A dispute arose over JCI's failure to pay G&G for its work, which resulted in G&G bringing claims for breach of contract, unjust enrichment, and violation of Missouri's Prompt Pay Act against JCI. In addition, a breach of surety bond claim was brought against JCI and its surety, Liberty Mutual Insurance Company ("Liberty Mutual").

The jury returned a verdict against JCI and Liberty Mutual in the amount of $445,408.94. The trial court entered judgment in favor of G&G and included prejudgment interest at the rate of nine percent pursuant to section 408.020.1 JCI and Liberty Mutual assert in their single point on appeal that the trial court erred in awarding prejudgment interest, arguing the parties agreed that no interest would be charged on amounts due. We affirm.

I. Preservation of Error

We must first consider whether the alleged error was preserved for our review given the failure of JCI and Liberty Mutual to file a motion for new trial pursuant to Rule 78.07(a).2 Rule 78.07(a) generally provides that "[i]n jury tried cases ... allegations of error must be included in a motion for a new trial in order to be preserved for appellate review." "The purpose of a motion for new trial is to give the [trial] court the opportunity to correct its own errors without appellate court intervention." Smith v. Brown & Williamson Tobacco Corp. , 410 S.W.3d 623, 640 (Mo. banc 2013) (citations omitted).

The issue of whether G&G was entitled to prejudgment interest pursuant to section 408.020 was first raised on March 16, 2017, in a motion for directed verdict filed by JCI and Liberty Mutual. The trial court heard argument on the issue and denied the motion. On March 20, 2017, JCI and Liberty Mutual filed a Trial Brief on Statutory Interest. The trial court heard from the parties on that day and revisited the issue on March 21, 2017. On March 30, *4952017, G&G filed a Motion for Award of Pre-Judgment Interest on Jury Verdict and Entry of Judgment along with supporting suggestions. JCI and Liberty Mutual filed a Memorandum in Opposition, and the trial court heard argument on May 15, 2017. On May 18, 2017, the trial court entered Judgment in favor of G&G, which included an award of prejudgment interest at a rate of nine percent. No after-trial motions were filed by JCI or Liberty Mutual.

The Missouri Supreme Court has held that "[t]he issue of prejudgment interest was properly presented to the trial court and adequately preserved for appeal" where, after the jury verdict, "both parties corresponded with the trial court about prejudgment interest[ ] and the court held two conferences on the issue." Brown v. Donham , 900 S.W.2d 630, 632 (Mo. banc 1995). While not specifically discussing the requirement found in Rule 78.07(a) that, following a trial by jury, a motion for new trial be filed in order to preserve an issue for appellate review, Brown clearly permits appellate review of an alleged error relating to an award of prejudgment interest that was first raised to and decided by the trial court.3

In light of the extensive briefing and argument by the parties before the trial court on the issue of prejudgment interest, we conclude, consistent with the Missouri Supreme Court in Brown, that the issue was properly preserved for appeal.

II. Prejudgment Interest Pursuant to Section 408.020

Having found that the issue was properly preserved for our review, we now consider whether the trial court erred by awarding G&G prejudgment interest at the statutory rate of nine percent.

A. Factual Background

The contract, including Attachment A containing the interest provision at issue, was signed by G&G on December 28, 2011, and transmitted to JCI on December 29, 2011. The interest provision stated: "Any pay estimate overdue by 60 days shall bear interest at the annual rate of 18% or the highest rate allowed by law, if lower. Retainage shall not be held out of payment." Douglas Adrian ("Adrian"), on behalf of JCI, struck through the entire provision with a single line, initialed "DA", and *496wrote "5% Retiange [sic]" in the margin. The contract was returned to William Dooley ("Dooley") of G&G. Near the writings of Adrian, Dooley initialed "WOD" and dated "1/9/12".

B. Discussion

Where an agreement is reached by the parties regarding the interest rate, even if the agreement is that no interest will be paid or established the interest rate to be zero percent, it will be enforced. See, e.g. , Manfield v. Auditorium Bar & Grill, Inc. , 965 S.W.2d 262, 269-70 (Mo. App. W.D. 1998) (holding that the parties' agreement to a rate of zero percent interest would be enforced). However, where no agreement is made, including where a contract contains a provision concerning interest but the rate is left blank, the creditor is entitled to interest at the rate designated by section 408.020. See § 408.020; Bank of Kirksville v. Small , 766 S.W.2d 770, 771 (Mo. App. W.D. 1989). Section 408.020 provides:

Creditors shall be allowed to receive interest at the rate of nine percent per annum, when no other rate is agreed upon, for all moneys after they become due and payable, on written contracts, and on accounts after they become due and demand of payment is made[.4 ]

Here, JCI and Liberty Mutual claim that the mutual striking of the provision in the contract relating to prejudgment interest equated to an agreement that no interest would be paid.5 They accordingly allege that the trial court erred by awarding interest at a rate of nine percent to G&G pursuant to section 408.020. G&G counters that the striking of the interest provision did nothing more than remove it from the parties' agreement, leaving the final contract silent on the issue of prejudgment interest. To resolve this conflict, we must look to the contract.

The primary rule of contract construction is to ascertain the intent of the parties and give effect to that intention. If a contract is unambiguous, the intent of the parties is to be discerned from the contract alone based on the plain and ordinary meaning of the language used.[6 ]
*497However, a contract may be ambiguous if it is susceptible to more than one interpretation, which is a legal issue determined by the court. If the ambiguity cannot be resolved within the four corners of the contract, the parties' intent can be determined by use of parol evidence. Resolution of the ambiguity may then be a factual issue to be resolved by the finder of fact.

Whelan , 379 S.W.3d at 846 (citations and internal quotation marks omitted). Whether the contract is ambiguous and whether G&G was entitled to prejudgment interest pursuant to section 408.020 are legal issues that we review de novo , but we defer to the trial court's factual or credibility determinations. See id.7

A general rule of contract interpretation or construction is that "stricken language is extrinsic and may not be resorted to in construing [a] ... contract." Maddick v. DeShon , 296 S.W.3d 519, 526 (Mo. App. W.D. 2009) (citing Gateway Frontier Props. v. Selner, Glaser, Komen, Berger & Galganski, P.C. , 974 S.W.2d 566, 570-71 (Mo. App. E.D. 1998) ); see also 17A C.J.S. Contracts § 419. "The rationale ... is that the writing excised from the agreement, whether by way of striking, erasing, or simply transferring the agreement to a new piece of paper without the stricken language, is not part of the agreement between the parties." Id. (citation omitted). Reliance on stricken language to interpret an otherwise unambiguous contract is error. Id.8

Setting aside the stricken language, the contract that remains is silent *498on the issue of prejudgment interest and susceptible to only a single interpretation-the parties did not enter into an agreement on the issue of prejudgment interest.9 Hence, we find the contract is not ambiguous.10 Accordingly, parol or other extrinsic evidence regarding the parties' intent cannot be considered. See Whelan , 379 S.W.3d at 846. As a result, the contract will be enforced as written without consideration of the stricken language. Thus, the trial court properly awarded G&G prejudgment interest pursuant to section 408.020.

Point denied.

III. Conclusion

The Judgment of the trial court, including the award of prejudgment interest at the rate of nine percent pursuant to section 408.020, is affirmed.

All concur.