Cape Fear River Watch v. North Carolina Environmental Management Commission, 368 N.C. 92 (2015)

June 11, 2015 · Supreme Court of North Carolina · No. 373A14
368 N.C. 92

CAPE FEAR RIVER WATCH, SIERRA CLUB, WATERKEEPER ALLIANCE, and MOUNTAINTRUE (f/k/a WESTERN NORTH CAROLINA ALLIANCE), Petitioners v. NORTH CAROLINA ENVIRONMENTAL MANAGEMENT COMMISSION, Respondent and DUKE ENERGY CAROLINAS, LLC and DUKE ENERGY PROGRESS, INC., Respondent-Intervenors

No. 373A14

Filed 11 June 2015

Appeal and Error — mootness—coal ash lagoons — superseding legislation

The Supreme Court considered whether the trial court erred by reversing a portion of a declaratory ruling issued by the North Carolina Environmental Management Commission (Commission) on 18 December 2012 relating to the application of the Commission’s groundwater protection rules to coal ash lagoons. The General Assembly’s enactment of Chapter 122 of the 2014 North Carolina Session Laws superseded the rule at issue with respect to coal ash lagoons located at facilities with active permits, and petitioners’ appeal from the Commission’s declaratory ruling was moot.

Appeal pursuant to N.C.G.S. §§ 7A-27(b)(l) and 150B-52 from an order on petition for judicial review entered on 6 March 2014 by Judge Paul C. Ridgeway in Superior Court, Wake County. On 10 October 2014, pursuant to N.C.G.S. § 7A-31(a) and (b)(2) and Rule 15(e)(2) of the North Carolina Rules Of Appellate Procedure, the Supreme Court on its own initiative certified the case for review prior to determination in the Court of Appeals. Heard in the Supreme Court on 16 March 2015.

Southern Environmental Law Center, by Austin D. Gerken Jr., Amelia Y Burnette, J. Patrick Hunter, and Frank Holleman, for petitioner-appellees.

Roy Cooper, Attorney General, by Mary L. Lucasse and Jennie Wilhelm Hauser, Special Deputy Attorneys General, for respondent-appellant.

Womble Carlyle Sandridge & Rice, LLP, by James P. Cooney III; and Hunton & Williams LLP, by Charles D. Case, Matthew F. Hanchey, Frank E. Emory, Jr., and Brent A. Rosser, for respondent-intervenor-appellants.

*93ERVIN, Justice.

The substantive issue before us in this case is whether the trial court erred by reversing a portion of a declaratory ruling issued by the North Carolina Environmental Management Commission (Commission) on 18 December 2012 relating to the application of the Commission’s groundwater protection rules codified at Title 15A, Subchapter 2L, “Groundwater Classification and Standards,” of the North Carolina Administrative Code, to coal ash lagoons. See 15A NCAC 2L .0101-.0417 (June 2014) [hereinafter Groundwater Rules], In view of our conclusion that the General Assembly’s enactment of Chapter 122 of the 2014 North Carolina Session Laws1 supersedes the rule at issue in this appeal with respect to coal ash lagoons located at facilities with active permits, see Act of Aug. 20, 2014, ch. 122, 2014 5 N.C. Adv. Legis. Serv. 77 (LexisNexis) [hereinafter Chapter 122], we vacate the trial court’s order and remand this case to the trial court with instructions to dismiss petitioners’ appeal from the Commission’s declaratory ruling on mootness grounds.

The present case stems from a dispute over the manner in which certain regulatory requirements should be applied to coal ash lagoons that received operating permits before 30 December 1983.2 At the time at which the present proceeding was commenced, unlined coal ash lagoons existed at fourteen coal-fired electric generating facilities located in North Carolina. These coal ash lagoons contained the residue from the combustion of coal used to generate electricity. These residual materials consisted of a mixture of water, coal combustion by-products, and other waste.3 All fourteen of the power generation facilities at issue in this case operate subject to National Pollutant Discharge Elimination System (“NPDES”) permits that were originally issued by the North Carolina Department of Environment and Natural Resources (“DENR”) and are subject to Groundwater Rules that have been adopted by the *94Commission. According to groundwater samples taken from monitoring wells located on the properties on which the coal ash lagoons are .located, levels of contamination that exceed the relevant groundwater standards have been reported near some lagoons associated with the coal-fired generating facilities at issue in this proceeding.

Section .0106 of Title 15A, Subchapter 2L of the North Carolina Administrative Code describes the corrective actions required when “groundwater quality has been degraded.” 15A NCAC 2L .0106 [hereinafter Rule .0106]. According to Rule .0106(c), which applies to sites that are either unpermitted or “deemed not permitted” pursuant to Rule .0106(e) (4) at which groundwater contamination exceeds authorized levels:

Any person conducting or controlling an activity which has not been permitted by the Division and which results in an increase in the concentration of a substance in excess of the standard, other than agricultural operations, shall:
(1) immediately notify the Division of the activity that has resulted in the increase and the contaminant concentration levels;
(2) take immediate action to eliminate the source or sources of contamination;
(3) submit a report to the Director assessing the cause, significance and extent of the violation; and
(4) implement an approved corrective action plan for restoration of groundwater quality in accordance with a schedule established by the Director or his des-ignee. In establishing a schedule the Director, or his designee shall consider any reasonable schedule proposed by the person submitting the plan.

Id. .0106(c). On 10 October 2012, Cape Fear River Watch, Sierra Club, Waterkeeper Alliance, and Western North Carolina Alliance filed a request that the Commission issue a declaratory ruling clarifying the application of the Groundwater Rules to coal ash lagoons. More specifically, petitioners requested the Commission to make the following rulings:

a) Operators of coal ash lagoons with NPDES permits first issued on or before December 30,1983, must take corrective action pursuant to 15A N.C. Admin. Code 2L .0106(c) when their activity results in an increase in *95the concentration of a substance in excess of groundwater .quality standards, whether or not groundwater quality standards have been exceeded at or beyond a compliance boundary around the lagoon;
b) Operators of coal ash lagoons with NPDES permits first issued on or before December 30,1983, must take immediate action to eliminate sources of contamination that cause a concentration of a substance in excess of groundwater quality standards, in advance of their separate obligation to propose and implement a corrective action plan for the restoration of groundwater quality contaminated by those sources; and
c) Operators of closed and inactive coal ash lagoons must implement corrective action as unpermitted activities pursuant to 15A N.C. Admin. Code 2L .0106(c) when they cause an increase in the concentration of a substance in excess of groundwater quality standards.

After the filing of this request for a declaratory ruling and a decision by petitioners and DENR to enter into certain stipulations relating to relevant facts, the Commission granted an intervention petition filed by Duke Energy Carolinas, LLC and Carolina Power & Light Company, an indirect subsidiary of Duke Energy Corporation, d/b/a Progress Energy Carolinas (“Duke”). After reviewing the record and hearing oral argument from counsel for the parties at a 3 December 2012 meeting, the Commission issued a declaratory ruling on 18 December 2012, concluding, in pertinent part, that:

16. Activities that do not meet the requirements of 2L .0106(e), including those permitted prior to December 30, 1983, are deemed unpermitted and are subject to the requirements of 2L .0106(c) applicable to persons conducting or controlling an activity (other than agricultural operations) that has not been permitted and which results in an increase in the concentration of a substance in excess of the standard.
17. The corrective action requirements in 2L .0106(c) (1) through (4) are not prioritized, and the immediate action to eliminate the source or sources of contamination requires responsible parties and the Division to follow the detailed procedures set forth in the entirety of the 2L Groundwater Rules.
*9618. The specific corrective actions enumerated in 15A NCAC 2L .0106(f)(1) through (4) that are required to be undertaken, including a site assessment and a corrective action plan for the abatement, containment or control of migration of any contaminants, require a reasonable amount of time to accomplish. The “immediate action” contemplated by 15A NCAC 2L .0106(c)(2) is action appropriate to the circumstances evaluated in the context of the 2L Groundwater Rules.

On 8 January 2013, petitioners filed a petition seeking judicial review of the Commission’s declaratory ruling in Superior Court, Wake County, in which they claimed that the Commission had misconstrued the applicable regulations and erroneously failed to construe the applicable regulations in the manner contended for by petitioners in their original request for declaratory relief. After the submission of legal memoranda from the parties, the trial court heard oral argument on 26 August 2013 concerning the issues raised by petitioners’ request for a declaratory ruling. On the same day, Duke submitted a supplemental brief informing the trial court about the enactment of Chapter 413 of the North Carolina Session Laws three days earlier. See Act of July 26, 2013, ch. 413, Sec. 46, 2013 N.C. Sess. Laws 1752, 1783-84 [hereinafter Chapter 413].4 According to Duke, the enactment of Chapter 413 rendered moot the first of the three rulings that petitioners sought to have the trial court make. In response, petitioners submitted a supplemental brief in which they acknowledged that the first ruling that they had requested the Commission to make had been rendered moot by the enactment of Chapter 413.

On 6 March 2014, the trial court entered an order determining that portions of the Commission’s decision were “plainly erroneous and inconsistent with the regulation.” More specifically, the trial court found that the first request contained in petitioner’s original request for a declaratory ruling had, as the parties agreed, been rendered moot by the enactment of Chapter 413;5 reversed the Commission’s decision with respect to petitioners’ second request for a declaratory ruling and concluded that, in the event of a violation of the applicable groundwater rules by an unpermitted entity, “immediate action” must be taken to *97“eliminate sources” of the contamination that caused the violation; and dismissed petitioners’ claim with respect to the third request for declaratory relief set out in their original petition relating to unpermitted coal ash disposal sites on the grounds that petitioners had, in fact, prevailed on that issue before the Commission given that the Commission’s “[r] uling concurs with [petitioners’] interpretation.” The Commission and Duke noted an appeal to the Court of Appeals from that portion of the trial court’s order relating to the second ruling requested in petitioners’ petition for a declaratory ruling. On 10 October 2014, this Court on its own motion certified this case for immediate' review prior to determination of this case by the Court of Appeals.6

On 20 August 2014, the General Assembly ratified Chapter 122, which became effective on 20 September 2014 after the Governor failed to either sign or veto it. Act of Aug. 20, 2014, ch. 122, 2014 5 N.C. Adv. Legis. Serv. 77 (LexisNexis).

“[W]henever during the course of litigation it develops that ... the questions originally in controversy between the parties are no longer at issue, the case should be dismissed, for courts will not entertain an action merely to determine *98abstract propositions of law. If the issues before the court become moot at any time during the course of the proceedings, the usual response is to dismiss the action.”

Messer v. Town of Chapel Hill, 346 N.C. 259, 260, 485 S.E.2d 269, 270 (1997) (per curiam) (ellipsis in original) (citations omitted). According to the Commission and Duke, the enactment of this legislation rendered the declaratory ruling that is before us in this case moot on the grounds that provisions of the legislation in question superseded Rule .0106(c) with respect to the manner in which groundwater violations occurring at facilities subject to active NPDES permits should be addressed. We. agree.

As rewritten by the General Assembly effective 20 September 2014, N.C.G.S. § 143-215.1(k), which addresses the proper response to a situation in which groundwater standard violations occur beyond a facility’s compliance boundary, provides that:

(k) Where the operation of a disposal system permitted under this section results in exceedances of the groundwater quality standards at or beyond the compliance boundary, the Commission shall require the per-mittee to undertake corrective action, without regard to the date that the system was first permitted, to restore the groundwater quality by assessing the cause, significance, and extent of the violation of standards and submit the results of the investigation and a plan and proposed schedule for corrective action to the Director or the Director’s designee . ... In establishing a schedule the Director or the Director’s designee shall consider any reasonable schedule proposed by the permittee.

N.C.G.S. § 143-215.1(k) (2014), as amended by ch. 122, Sec. 12(a), 2014 5 N.C. Adv. Legis. Serv. at 123 (added language in italics). Although petitioners agree that the rewritten version of N.C.G.S. § 143-215.1(k) eliminates the distinction between facilities that were permitted before 30 December 1983 and facilities that were permitted after that date by providing that all permitted facilities, “without regard to the date that the system was first permitted,” are subject to the corrective action requirements of Rule .0106(d), petitioners contend that the enactment of the revised version of N.C.G.S. § 143-215.1(k) does not have the effect of mooting the trial court’s ruling with respect to the second issue posed in their original petition for declaratory relief given that the new statutory language does not alter the regulatory requirements applicable to *99disposal sites that do not hold active permits issued pursuant to N.C.G.S. § 143-215.1.7 We do not find petitioners’ contention persuasive.

Any consideration of the validity of petitioners’ response to the mootness contention advanced by the Commission and Duke must begin with an understanding that the only issue before us at this time is the correctness of the trial court’s ruling with respect to the second issue set out in petitioners’ original request for a declaratory ruling. In that portion of their filing, petitioners requested the Commission to determine that “[operators of coal ash lagoons with NPDES permits first issued on or before December 30, 1983, must take immediate action to eliminate sources of contamination that cause a concentration of a substance in excess of groundwater quality standards.” (Emphasis added.) As a review of its plain language clearly indicates, the second request for a declaratory ruling set out in petitioners’ petition related solely to facilities holding an NPDES permit. By contrast, the third request for a declaratory ruling set out in petitioners’ petition applied to “[operators of closed and inactive coal ash lagoons.” Although petitioners correctly assert that the second request set out in their petition for a declaratory ruling is only moot as applied to facilities with active permits, their second request for a declaratory ruling was limited to facilities with such permits. As a result, the only issue that, in petitioners’ view, remains viable following the enactment of the current version of N.C.G.S. § 143-215. l(k) is not properly before the Court.

Assuming, without deciding, that the second requested ruling set out in petitioners’ request for a declaratory ruling could apply to facilities that lack active permits, we believe that the issue that is currently before us is moot for an entirely different reason. The trial court’s unchallenged findings of fact establish that “[tjhere is no evidence of record of any closed or inactive coal ash lagoons.” “A trial court’s unchallenged findings of fact are presumed to be supported by competent evidence and [are] binding on appeal.” Mussa v. Palmer-Mussa, 366 N.C. 185, 191, 731 S.E.2d 404, 409 (2012) (alteration in original) (citation and internal quotation marks omitted). As this finding suggests, a careful examination of the uncontradicted evidence contained in the record that has been presented for our review in this case tends to show that all facilities at *100which coal ash lagoons were located did, in fact, hold an active NPDES permit.8 As a result, the evidence before us in this case reinforces our conclusion that this case has been rendered moot as a matter of both law and fact by virtue of the enactment of the revised version of N.C.G.S. § 143-215.1(k).

Finally, petitioners contend that we should review the correctness of the trial court’s resolution of the issue posited by the second request for a declaratory ruling set out in their original petition given that this issue involves a question of extraordinary public interest. “In state courts the exclusion of moot questions from determination is not based on a lack of jurisdiction but rather represents a form of judicial restraint.” In re Peoples, 296 N.C. 109, 147, 250 S.E.2d 890, 912 (1978) (citations omitted), cert. denied, 442 U.S. 929, 99 S. Ct. 2859, 61 L. Ed. 2d 297 (1979). “Even if moot... this Court may, if it chooses, consider a question that involves a matter of public interest, is of general importance and deserves prompt resolution.” N.C. State Bar v. Randolph, 325 N.C. 699, 701, 386 S.E.2d 185, 186 (1989) (per curiam) (citations omitted). While the appropriate response to the environmental issues associated with the operation of coal ash lagoons is clearly a matter of significant public interest, this Court’s role in the resolution of such questions is limited to determining the content of existing law and ensuring that existing law is appropriately applied to the relevant facts. At this point, the record does not contain any indication that any decision that we might make with respect to the correctness of the trial court’s resolution of the second request for a declaratory ruling set out in petitioners’ petition would have any practical impact. In addition, it is clear that the General Assembly has taken an active role in the proper resolution of the issues that petitioners sought to have addressed in the petition for a declaratory ruling. By adopting Chapter 122, the General Assembly sought to address the public’s understandable concern about the effect of the operation of coal ash lagoons on the ground and surface waters in North Carolina. In light of these considerations, we believe that we should refrain from issuing what amounts to an advisory opinion concerning any impact of the applicable regulation on any non-permitted coal ash lagoons that may, contrary to the record evidence, actually exist. As a result, we hereby vacate the trial court’s order and remand this case to the trial court *101with instructions to dismiss petitioners’ appeal from the Commission’s declaratory ruling on moótness grounds.9

VACATED AND REMANDED.

Justice EDMUNDS did not participate in the consideration or decision of this case.