Skinner v. Gaither Corp., 234 N.C. 385 (1951)

Oct. 31, 1951 · Supreme Court of North Carolina
234 N.C. 385

M. L. SKINNER v. GAITHER CORPORATION.

(Filed 31 October, 1951.)

1. Arbitration and Award § la—

An agreement to arbitrate all disputes, claims and questions arising in performance of the work is not an agreement to arbitrate the contract price for tbe construction of the building, and therefore action by the contractor to recover balance due on the contract in addition to amount due for labor and materials used in repairing and replacing plastering which fell, is not barred by the arbitration agreement as to the action for balance of contract price, at least, and demurrer for failure of the complaint to state a cause of action is properly overruled.

a. Pleadings § 19c—

If the complaint in any part or to any extent is sufficient to state a cause of action, demurrer thereto is properly overruled.

3. Arbitration and Award § la—

The Uniform Arbitration Act does not apply to an agreement to arbitrate differences under contract when the arbitration agreement is executed at the time of the contract, since the Act applies only to agreements to arbitrate executed after controversy has arisen. G.S. Chap. I, Art. 45.

4. Arbitration and Award § 2—

An agreement to arbitrate all disputes or questions arising under a contract incorporated into the contract as a part thereof cannot bar either party from maintaining an action for breach of the contract, since the courts will not decree specific performance of'the agreement to arbitrate either directly or indirectly by refusing to entertain a suit prior to arbitration.

Appeal by defendant from Carr, JMay Term, 1951, CeaveN.

Affirmed.

Civil action to recover (1) balance due on contract to erect a building, and (2) amount due for labor and material used in repairing and replacing plastering and for commissions, beard on demurrer.

Plaintiff, a building contractor, agreed to erect a building on property of defendant for tbe contract price of $88,454. Tbe written contract contained provision for tbe arbitration of “all disputes, claims or questions” subject to arbitration under tbe contract “in accordance with tbe provisions, tben obtaining, of tbe Standard Form of Arbitration Procedure of Tbe American Institute of Architects.”

Tbe architect was to make decisions on all claims of tbe owner or contractor and on all other matters relating to tbe execution and progress of tbe work or tbe interpretation of tbe contract documents and bis decisions, except as to “matters relating to artistic effect” were made subject to arbitration on written notice and demand of either party.

*386After tbe building was completed and occupied by a tenant, part of tbe ceiling plastering fell. Plaintiff and defendant agreed that plaintiff should repair tbe ceiling, substituting Cellotex or fiberboard for tbe plaster and that tbe defendant would pay tbe plaintiff tbe cost of labor and material plus 10% commission unless it should be determined later that tbe falling of tbe plaster was due to tbe fault of tbe plaintiff. Tbe question of responsibility was reserved for future determination under the original contract.

Tbe total contract price of said repairs was $7106.56.

The plaintiff instituted this action to recover said amount plus $2,000 alleged to be due on tbe contract price and in bis complaint alleges tbe facts substantially as stated, except that tbe arbitration agreement is made a part of tbe complaint by reference only.

Tbe defendant demurred for that tbe complaint fails to state a cause of action in that it is not made to appear that tbe plaintiff has complied with tbe arbitration agreement in tbe particulars specified in tbe demurrer; that in said contract it is stipulated “that tbe decision of tbe arbitrators shall be a condition precedent to any right of legal action that either party may have against tbe other”; and that under tbe contract plaintiff must first resort to arbitration before be may maintain this action.

Tbe demurrer was overruled and defendant appealed.

Barden, Stith & McGotter, W. B. R. Guión for plaintiff appellee.

Worth & Horner, R. E. Whitehurst for defendant appellant.

BabNhill, J.

Tbe amount to be paid to tbe plaintiff for constructing tbe building and tbe balance, if any, still due and unpaid thereon are not subject to arbitration under tbe contract! Plaintiff sues, in part, to recover an alleged balance due. In this respect, in any event, tbe complaint is sufficient to repel tbe demurrer. Mills Co. v. Shaw, Comr. of Revenue, 233 N.C. 71, and cases cited.

But defendant insists that as to tbe repair bill the arbitration provisions of tbe contract prevail and preclude plaintiff’s right to resort to the courts until after tbe arbitration is bad as agreed by tbe parties. Its position in this respect is likewise untenable.

This is not a contract to arbitrate under tbe provisions of our Uniform Arbitration Act. That Act, G.S. Chap. 1, Art. 45, applies only to agreements to arbitrate controversies existing between tbe parties at tbe time of tbe execution of tbe agreement to adopt this method of settlement. Hence, decision here is controlled by our cases pertaining to contracts of this type to which tbe common law rule applies.

It is settled law in this jurisdiction, as in most others, that when a cause of action has arisen, tbe courts cannot be ousted of their jurisdiction *387by an agreement, previously entered into, to submit the rights and liabilities of the parties to arbitration or to some other tribunal named in the agreement. Kelly v. Trimont Lodge, 154 N.C. 97, 69 S.E. 764; Williams v. Manufacturing Co., 153 N.C. 7, 68 S.E. 902; Nelson v. R. R., 157 N.C. 194, 72 S.E. 998; Hargett v. DeLisle, 229 N.C. 384, 49 S.E. 2d 739; Brown v. Moore, 229 N.C. 406; Stephenson v. Ins. Co., 54 Me. 55; Blodgett Co. v. Bebe Co., 26 A.L.R. 1070; Anno. 26 A.L.R. 1077 and 135 A.L.R. 80; Anno. 47 L.R.A. ns 352; 3 A.J. 871 (See numerous eases cited in notes).

At any time before an award is rendered under the contract, either party may elect to breach his contract, 3 A.J. 891, and seek his remedy in the tribunal provided by law, Carpenter v. Tucker, 98 N.C. 316; Williams v. Manufacturing Co., supra; Tarpley v. Arnold, 226 N.C. 679, 40 S.E. 2d 33; 3 A.J. 871, and “where the right of action is complete without an arbitration, an agreement is not taken out of the scope of the rule by an express stipulation that suit shall be subject to the condition that arbitration first be had.” 3 A.J. 872.

The rule comes to this: The agreement of the parties to arbitrate is a contract. The relation of the parties is contractual. Their rights and liabilities are controlled by the law of contract. A breach of the contract may give 'rise to a cause of action for damages, but the contract itself is not a defense against a suit on the cause of action the parties agreed to arbitrate. Carpenter v. Tucker, supra; Sprinkle v. Sprinkle, 159 N.C. 81, 74 S.E. 739. In an action on the contract the courts will not decree specific performance of the agreement. Neither will they, by indirection, compel specific performance by refusing to entertain a suit until after arbitration is had under the agreement.

It is not amiss to note here that the courts uniformly recognize the difference between an agreement to arbitrate and a submission consummated by an award. After the agreement has been consummated by an award there can be no revocation. Nelson v. R. R., supra; Williams v. Manufacturing Co., supra; 3 A.J., sec. 41, p. 870. The award is binding on the parties and will be enforced.

It follows that the executory agreement to arbitrate controversies which might arise in the course of the fulfillment of the contract between the parties is no bar to this action.

The judgment overruling the demurrer is

Affirmed.