*497Appeal op IiiteeveNeb, East TenNEssee NatioNal BaNic.
In January, 1926, tbe contractor, R. G. Hill & Company, borrowed from tbe East Tennessee National Bank tbe sum of $5,000, executing its promissory note as evidence thereof, a portion of wbicb was used in paying laborers for work done in and about tbe construction of said highway. Tbe balance of this loan was used for other purposes connected with tbe construction of said projects.
No assignment was taken from any of tbe laborers or other persons receiving payment from these funds, and tbe note itself does not show for what purpose tbe money was loaned.
Tbe referee held that tbe loan of $5,000 made by tbe East Tennessee National Bank to tbe contractor was not covered by tbe bond in suit, and this ruling was approved by tbe judge of tbe Superior Court. The appeal of tbe intervener challenges tbe correctness of tbe conclusion reached.
Tbe judgment accords with tbe general bolding that a bank furnishing money to a contractor doing public work, for use in paying tbe claims of laborers and materialmen, without more, does not come within tbe protection of a statutory bond conditioned to pay all persons supplying tbe principal with labor or materials in tbe prosecution of bis work. Bank v. Clark, 192 N. C., 403, 135 S. E., 123; Nat. Surety Co. v. Jackson County Bank, 20 Fed. (2nd), 644.
Tbe terms of tbe bond in suit, so far as applicable to tbe claim of tbe intervener, are no broader than tbe provisions of tbe statute; hence tbe ruling of tbe Superior Court would seem to be correct. Tbe judgment in this respect is affirmed.
Appeal oe SoutheeN Subety CompaNY.
Four separate and distinct propositions are presented by tbe appeal of tbe Southern Surety Company. ■ They will be considered seriatim.
Claim oe Bbysoh City Bauic.
Tbe Bryson City Bank extended to D. S. Hill, foreman of R. G. Hill & Company, credit to tbe extent of $98.57 with wbicb it is alleged be paid certain persons having claims against tbe contractor for labor performed in and about tbe construction of tbe work, etc., but neither D. S. Hill nor tbe bank took any assignment or assignments from tbe persons or employees to whom this money was advanced or paid.
Tbe referee held that tbe claim of tbe Bryson City Bank for $98.57 advanced to D. S. Hill, as aforesaid, was not covered by tbe bond in suit, *498but tbis ruling was reversed by the judge of tbe Superior Court, upon exceptions duly filed to the report of the referee.
It seems to us that the Bryson City Bank is in no better position than the East Tennessee National Bank and that the claim of neither comes within the provisions of the bond or the purview of the statute. The conclusion of the referee in this respect should have been approved.
Claim of R. L. Tulloh.
R. L. Tulloh was employed by the contractor “as a walking-boss or superintendent” in the construction of said highway, and he “performed a class or kind of work necessary to the construction of said highway and road projects.” The said contractor is now indebted to Tulloh in the sum of $648.93 for such work done in and about the construction of the highway in question.
It was the conclusion of the referee, approved by the judge of the Superior Court, that the bond in suit, by fair construction, was intended to cover the claim of R. L. Tulloh. The Surety Company excepts to this ruling and relies upon the decision in Moore v. Industrial Co., 138 N. C., 304, 50 S. E., 687, as authority for its position. The claimant, on the other hand, calls attention to the provisions of the bond and cites the case of Cox v. Lighting Co., 152 N. C., 164, 67 S. E., 477, as supporting his position.
In view of the character of work required of the claimant, which does not appear in detail on the record, we are not able to say that there is error in the ruling; hence the judgment in this respect will be upheld.
Appellant must show error; it is not presumed. Jones v. Candler, ante, 382.
Claim of D. S. Hill.
The claim of D. S. Hill is for $1,044.98, wages as foreman, and $249.94 advanced by him to the “petty cash account” of the contractor and used in making repairs to the machinery from time to time, purchasing materials and paying freight thereon.
The referee concluded that both of these items were-covered by the bond in suit, and this was approved by the judge of the Superior Court.
The ruling is correct in so far as it affects the amount due for services as foreman. Cox v. Lighting Co., supra. But the $249.94, advanced to the “petty cash account” of the contractor, we apprehend, is no more than a loan of that amount. No assignments were taken for purchases of materials made from said account. In this respect the claimant would seem to stand on a parity with a bank which loaned money to the contractor without taking any assignment of the claims paid. The judgment should be modified accordingly.
*499Claim of W. J. Savage & CompaNy.
Tbe contractor while at work on the highway in question, borrowed two “sticks” from the Dempster Construction Company for use in repairing its steam shovel, and on 24 April, 1926, it purchased from W. J. Savage & Co. two steam shovel “sticks” at the price of $230, and ordered them shipped to the Dempster Construction Company at Knoxville, Tenn., to replace the “sticks” borrowed. The “sticks” sold by claimant to the contractor were never shipped to the Forney Creek Highway projects and never used by the contractor in the construction of said roads.
The referee concluded that as the transaction simply amounted to “swapping sticks,” the claim of W. J. Savage & Company against E. G-. Hill & Company was properly covered by the bond in suit, and this was approved by the judge of the Superior Court. The Surety Company assigns such ruling as error.
We think the “sticks” furnished the contractor, for which the Southern Surety Company would be liable under its bonds, were those' supplied by the Dempster Construction Company, which have been paid for, not in money, but with other “sticks” purchased from the claimant. W. J. Savage & Company, therefore, is not entitled to enforce collection of its claim against E. G-. Hill & Company out of the bond executed by the Southern Surety Company.
Let the cause be remanded with direction that judgment be modified in accordance with this opinion, and as thus modified it will be affirmed.
Modified and affirmed.