McCausland v. R. A. Brown Construction Co., 172 N.C. 708 (1916)

Dec. 19, 1916 · Supreme Court of North Carolina
172 N.C. 708

J. N. McCAUSLAND & CO. v. R. A. BROWN CONSTRUCTION COMPANY, M. L. BROWN, A. M. BROWN et als.

(Filed 19 December, 1916.)

1. Indemnity — Insurance—Contracts—Interpretation.

A bond guaranteeing performance of a building contract will be construed with the contract in determining the liability of the sureties to third persons furnishing materials, etc., for the building.

2. Same — Mechanics’ Liens — Principal and Surety.

Sureties on a bond indemnifying the owner of a building .contracted to be erected are not liable for material, etc., used in the building when by the clearly expressed terms of the bond, construed with the contract, the indemnity is solely for the benefit of the owner, and he has sustained no loss.

*7098. Same — Mechanic's Lien — Principal and Surety.

Our public policy forbids the filing and enforcement of a lien for material used in the erection of a public building, in this case a building for a public school.

4. Same — Schools—Principal and Surety.

The school committee of a town contracted for the erection of a public school building and required from the contractor a bond indemnifying the committee against liens or claims of material men, etc., and for the proper performance of the contract. In interpreting the bond with the contract in this case it is Held, that the interest of the owner or obligee was alone considered and protected, and that the sureties are not liable to material men, who could not enforce a valid claim against the school committee or lien on the completed building accepted and used for the contemplated purpose.

5. Mechanics’ Liens — Public Buildings — Indemnity Bonds — Principal and Surety — Statutes.

Chapter 150, sec. 2, Laws 1913, making it a misdemeanor for the authorized persons having charge of the erection of a public building to omit to take a bond from the contractor indemnifying those furnishing the material used therein against loss, does not expressly or by implication provide that a bond taken omitting this provision shall be available to the material men; and where the bond fails in this respect, no liability attaches to the sureties thereon.

Civil actioN tried before Carter, J., and a jury, at February Term, 1916, of MeckleNburg.

On the trial it was made to appear that in July, 1914, the board of school commissioners of Concord, N. C., contracted with the Brown Construction Company to provide the material and labor for erection and completion of a public school building in said city at a cost of $11,236 and required said contractor to enter into a bond in the sum of $5,000 for the proper performance of the contract, etc. This bond was given by the construction company with the individual defendants as sureties and said building has been “erected, constructed, and completed,” and same has been duly accepted by the board and paid for. That during construction of said building, plaintiffs, under a contract with the construction company, furnished the material and labor to put on and complete the roofing on said building, to the amount of $771.41, and the same and every part thereof is now due and owing plaintiff from the construction company. That later the construction company became insolvent and plaintiff instituted the present action against said company and the sureties on the bond to recover the amount claimed to be due.

The court charged "the jury, in effect, that if they believed the evidence, both the company and the individual defendants, sureties on the bond, were liable for the debt.

*710There was verdict for plaintiff against all of defendants for $771.41. Judgment, and the individual defendants excepted and appealed.

McMinch & Justice for plaintiff.

Glarlcson & Taliaferro, L. T. HaHsell, and W. Q. Means for defendant.

íIokb, J.

The contract for the erection of the building makes stipulation, among other things, “That the contractors shall and will provide all the material and perform all the work for the erection and completion of a high school building on the lot of the owners in the city of Concord, etc., at the price of $11,236,” etc. And further: “If at any time there shall be evidence of any lien or claim for which, if established, the owners of the said premises might become liable, and which is chargeable to the contractors, the owners shall have the right to retain out of any payment then due or thereafter to become due an amount sufficient to completely indemnify them against such lien or claim. Should there prove to be any such claim after all such payments are made, the contractors shall refund to the owners all moneys that the latter may be compelled to pay in discharging any lien on said premises made obligatory in consequence of the contractor’s default.” And again: “The contractors further agree to furnish the owners, free of cost to the owners, á satisfactory indemnity bond in the sum of $5,000, to guarantee the faithful performance- of the contract and to indemnify the owners against liability • from accidents to persons or their property during the erection of the building.” The conditions of the $5,000 indemnity bond, signed by defendant, is as follows: “Now, therefore, if the above bounden R. A. Brown Construction Company shall well and truly perform and fulfill all the covenants and agreements mentioned in said contract and specifications for the erection and completion of the said building, to be performed and fulfilled as therein set forth, and to the written approval of the said architects, and will and shall save and keep harmless the said board of school commissioners of the city of Concord and the said building and the land on which the same is erected from all and every claim for materials, labor, or otherwise incurred by reason of erection and completion of said building, and shall turn over the said building to the said board of school commissioners of the city of Concord free and clear from all liens or claims for material or labor, and faithfully perform the said contract and save the said board of school commissioners of the city of Concord against all liability from accident to person or property during the erection of said building, then this obligation to be void; otherwise, to remain in full force and virtue.”

*711Upon these, the portions of the contract and bond more directly relevant, we are of opinion that plaintiff bas shown no cause of action against the sureties. There are many decisions with us to the effect that in case of these guarantee bonds or written contracts of indemnity third persons interested and having claims, though not named, may institute action thereon and recover when it appears by “express stipulation or by fair and reasonable intendment that their rights and interests were contemplated and being provided for.” Morton v. Water Co., 168 N. C., 582; Withers v. Poe, 167 N. C., 372; Supply Co. v. Lumber Co., 160 N. C., 428; Voorhees v. Porter, 134 N. C., 591; Town of Gastonia v. Engineering Co., 131 N. C., 363; Gorrell v. Water Supply Co., 124 N. C., 328.

In case of building contracts with bonds guaranteeing performance on the part of the contractor, it is held that in determining the question of the sureties’ liability to third persons the contract and bond shall be construed together. Mfg. Co. v. Andrews, 165 N. C., 285, and recoveries on the part of claimants of that character, usually laborers and material men, not expressly named, are sustained where it appears that the guarantee bond, in express terms,, provides for liability to such persons, as in Morton v. Light and Power Co., supra; Gorrell v. Water Supply Co., supra; or when there is stipulation that claims of this kind shall be paid by the contractor, the case presented in Supply Co. v. Lumber Co., supra, and Gastonia v. Engineering Go., an application of the principle approved by many authoritative decisions elsewhere. Knight & Jillson Co. v. Arthur Castle, 172 Ind., 97, reported also in 42 L. R. A., U. S., 573, with note by the editor; Ocho v. Carnahan Co., 42 Ind. App., 157; Brown v. Maryland, 22 Ind. App., 652; Jordan v. Kavanaugh, 63 Iowa, 152, and eases cited in note to Cleveland Roofing Co. v. Gaspard, Anno. Oases, 1916 A, 39 vol., pp. 745-758, or where the language of the instrument is sufficiently ambiguous to permit of construction and the terms of the obligation and the attendant facts and circumstances, relevant and permissible in their proper interpretation, show by fair and reasonable intendment that claimants of that character are to be provided for; an instance presented in Shoaf v. Ins. Co., 127 N. C., 308, and the eases of Voorhees v. Porter and Withers v. Poe may be referred, in part, to same position. But the principle does not extend to bonds of indemnity in strictness, for the owner or obligee named, as where there is stipulation in express terms that the indemnity is for the owner alone. Mfg. Co. v. Andrews, supra, or when, from a perusal of the relevant clauses of the contract, it is clear that the' interest of the owner or obligee named is alone considered and protected. Clark v. Bonsal, 157 N. C., 270, or where there is a stipulation to relieve from liens, *712and tbe contract, as in tbis instance, concerns a building for tbe public, and tbe assertion of a lien is forbidden and prevented by a public policy, tbe private right in sucb cases being properly subordinated to tbe public interests. Hardware Co. v. Graded Schools, 151 N. C., 507; Smith v. Bowman, Utah, reported in 9 L. R. A., U. S., 889; Townsend v. Roofing Co., 18 Ind. App., 568.

On careful consideration of tbis contract and tbe bond to secure same, it is clear tbat, so far as tbe sureties on tbe bond are concerned, tbe obligation is one strictly of indemnity towards tbe owner, and tbat tbe claims of laborers or material men were in no way considered or provided for except in so far as necessary to effect tbe primary purpose. In tbe contract, tbe stipulation is, first to provide tbe material and labor to complete tbe building, simply tbe usual form of obligation between tbe owner and contractor, and otherwise has no special significance. Mfg. Co. v. Andrews, supra.

Further on tbe subject, there is provision if at any time there shall be evidence of any lien or claim for which, if established, tbe owner might become liable and which is chargeable to contractors; and, again: “Tbe bond is to guarantee tbe faithful performance of tbe contract and to indemnify tbe owners against liability from accidents,” etc. And tbe bond given, providing for tbe faithful performance: “and will save and keep harmless tbe said board of school commissioners of tbe city of Concord, and tbe said building and tbe land on which tbe same is erected, from all and every claim for material, labor, or otherwise incurred, etc., and shall turn over tbe said building to said board free from all claims for material,” etc. Not a word in either contract or bond, or tbe two together, looking to any obligation assumed to tbe material men or for their benefit, but only so far as required to protect tbe owners and tbe building and land on which it is situate from liens or claims which might be made effective against them.

Tbe facts in evidence showing tbat every condition of tbe bond has been met, the building completed according to specifications and turned over to public authorities free from any and all claims against them, the building or tbe land on which tbe same is situate, no liability should attach to the sureties, and tbe judgment as to them must be reversed. Townsend v. Cleveland Co., 18 Ind. App., supra.

We are not inadvertent to a line of authorities cited for plaintiffs tbat in claims of tbis kind statutes and bonds looking to tbe protection of material men and laborers should receive a liberal interpretation, notably, tbe case of United States to the use of Hill v. Surety Co., 200 U. S., 197. In tbat ease a Federal statute required tbat persons making formal contracts with tbe United States for tbe construction or repair of public buildings should enter into a bond stipulating, among *713other tilings: “That the contractor or contractors shall promptly make payments to all persons supplying labor or 'materials in the prosecution of the work provided for in the contract,” etc., and the bond had been given in terms as required by the law. Applying, as stated, the principle of a liberal interpretation of such statutes and contracts, the Court held that there was nothing to restrict liability in the bond to claimants who furnished material, etc., directly to the contractor, but that the statute, by correct construcion, would extend to and provide for claimants who had supplied subcontractors for use in the building, etc. But neither this nor the other authorities cited, nor the principle upon which they proceed, apply to a case like the present, in which the bond is clearly one of indemnity towards the owner. And, in reference to our own statute requiring that a bond to protect such claimants shall be taken, Laws 1913', ch. 150, sec. 2, if the statute had provided that any bond taken in such cases should inure to the benefit of laborers and material men, this might be construed as constituting a part of contracts to which the statute applied. White v. Kincaid, 149 N. C., 415. The law, however, is not so drawn, but requires that “every county, city, or other municipal corporation entering into a contract for constructing, repairing, etc., a public building shall require a contract in a sum specified, conditioned for the payment of all labor and material, etc.” While the statute makes the failure to take such a bond a misdemeanor on the part of the official charged with the duty, and while, in case of ambiguity, a presumption might arise in favor of its proper performance, it only directs that a bond to that effect shall be taken, and does not apply to a case where it is clear, as stated, that no such bond was taken and no such obligation assumed. As a matter of fact, it is no doubt true that both parties acted in ignorance of the statutory requirement, and merely filled out a bond in the old form, designed and intended to protect-the public and the building and the land on which the same is situate, and a direct obligation to the material men was in no way contemplated or provided for.

Thera is error, and the judgment against the sureties is reversed and action dismissed.

Reversed.