Morganton Manufacturing & Trading Co. v. Andrews, 165 N.C. 285 (1914)

April 15, 1914 · Supreme Court of North Carolina
165 N.C. 285

MORGANTON MANUFACTURING AND TRADING COMPANY et als. v. E. L. ANDREWS and C. A. CREWS.

(Filed 15 April, 1914.)

1. Liens — Material Men — Contract—Principal and Surety — Bond— Interpretation.

Where the material man sues the owner of the building, claiming a lien thereon for material furnished, and seeks to hold the surety liable under a bond indemnifying the owner against loss, if any, arising to him under the contract, the bond of indemnity and the agreement with the contractor should be construed together.

2. Same — Contracts Expressed — Payment Under Contract — .Liability of Surety.

Where the owner of a building erected under an agreement with the contractor that the latter should build the house specified for a sum certain and turn it over to the owner completed, stipulations in the contracts that the contractor furnish the materials add nothing to the agreement of the contractor already expressed; and when the bond expressly states that it was solely an indemnity against personal loss to the owner, there can be no liability of the surety implied contrary to the terms of the writing, and the owner hot being liable to the lienor who has failed to notify him of his lien when there was money due by him to the contractor, there can be no liability on the part of the surety thereon. Supply Go. v. Lumber Go., 160 N. 0., 428, etc., cited and distinguished.

*2863. Statutes — Codification—Interpretation—Meaning Reconciled.

Statutes enacted upon the same subject-matter should be con-trued together and their meaning reconciled when possible, and where various enactments have been codified by the Legislature, it is permissible, in their construction, for the courts to regard the original statutes and their history in the light of former decisions.

4. Liens — Statutes — Interpretation — Material Men — Funds Due-Moneys Prorated.

•Where the owner of a building erected under contract has not sufficient funds in. his hands to pay all the lienors thereon for material furnished, the amount due the contractor, subject to the liens, shall be distributed by the owner among the several claimants under the provisions of section 2023 of the Revisal; and construing this section with other relevant sections of the Revisal, it is held that it does not conflict with section 2035, requiring “that liens created and established by this chapter '(48) shall be paid and settled according to priority of the notice of the lien filed with the justices or the cleric,” for this latter section relates to liens filed with the proper officers, and does not affect the provisions as to subcontractors who acquire a lien by notice to the owner.

AppEAX-by plaintiff from Lane, J., at September Term, 1913, of Forsyth.

This is an action by the Morganton Manufacturing and Trading Company and other creditors to enforce liens for materials furnished.

The defendant E. L. Anderson was the owner of a lot in Winston, and- on 28 August, 1911, he entered into a contract with the defendant C. A. Crews as contractor, by which the latter agreed to build a house thereon for $4,600.

■The parts of the contract material to be set out are:

“The contractor shall and will provide all the materials and perform all the work for the erection and completion of a two-story frame- residence located on lot fronting Brookstown Street, in the city of Winston, N. C.

“To secure the. true and faithful performance of all and every 'of the covenants and agreements herein mentioned, the party of the first part shall, at his own expense, within ten days from this *287date, furnish said party of the second part a bond signed by the American Surety Company in the sum of $1,000, to protect the second party against damage suits, for personal injuries, for liens, for material or labor; to remain in full force and effect until representation of satisfactory evidence of the satisfaction of all such claims.

“The final payment shall be made within ten days after the completion of the work included in this contract, and all payments shall be due when certificates for the same are issued.

“If at any time there shall be evidence of any lien or claim for which, if established, the owner of the said premises might become liable, and which is chargeable to the contractor, the owner shall have the right to retain out of any payment then due or thereafter to become due an.,amount sufficient to completely indemnify him against such lien or claim. Should there prove to be any such claim after all payments are made, the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging any liens on said premises'made obligatory in consequence to the contractor’s default.”

By agreement, the bond provided for in the contract was executed by the defendant the Maryland Casualty Company, instead of by the American Surety Company, and the penalty in the bond was $4,600 and not $1,000.

The' bond contains the following provisions, among others:

“Now,'therefore, the'condition of this obligation is such that if the said principal,shall faithfully perform said contract on his part, according to the terms, covenants, and conditions thereof (except as hereinafter provided), then this obligation shall be void; otherwise, to remain in full force and effect.

“This bond is executed by the surety upon the following express conditions, which shall be conditions precedent to the right of the owner to recover hereunder:

' “The surety shall not be liable under this bond to any one except the owner; but it is agreed that the owner, in estimating his damage, may include the claims of mechanics and material men, arising out of the performance of the contract, and paid *288by him, only when the same by the statutes of the State where the contract is to be performed are valid liens against his property.”

The Morganton Manufacturing and Trading Company furnished materials for said building, and which were used therein, of the value of $1,063.31, and the other creditors materials of the value of $1,87.7.18, all of which were furnished under contract with the said Crews, contractor.

All of said creditors filed notice of their claims with the defendant Anderson, and at the time of filing such notice there was due the contractor, Crews, who is insolvent, by the owner, Anderson, $1,328.39.

Said creditors also filed notice of lien in the office of the clerk of the Superior Court, the notice of lien of the Morganton Manufacturing and Trading Company being the first filed.

The matters in controversy were tried before a referee, Mr. J. E. Alexander, and upon the facts found by him, substantially as herein stated, his Honor adjudged that the Maryland Casualty Company was not liable to the creditors, and that the balance in the hands of Anderson should be distributed pro rata among all the creditors, to which the creditors excepted and appealed.

The creditors other than the Morganton Manufacturing and Trading Company except to (1) “the refusal of the court to find as a matter of law that the Maryland Casualty Company was bound to said parties who furnished material in the completion of the house of E. L. Anderson; and further except to the judgment of the court that the bond executed by the surety company was bound only to the extent of protecting E. L. Anderson, and did not protect material men and laborers for work done and material furnished.”

The Morganton Manufacturing and Trading Company excepts (1) “To the ruling of the court overruling the said plaintiff’s first exception to the report of the referee, and holding that this plaintiff was not entitled to priority by reason of filing the first lien in the office of the clerk of the Superior Court of Forsyth County, as set forth in said exception, which is hereby *289referred to and'made a part hereof as fully as if written herein.” (2) “To the ruling of the court in overruling said plaintiff’s second exception to the report of the referee, and holding that the parties were entitled to prorate in-the fund, and that this plaintiff was not entitled to priority, as set forth in said exception which is hereby referred to and made a part hereof as fully as if written herein.” (3) “To the judgment of the court that the fund should be prorated between all claimants, notwithstanding this plaintiff had filed the first lien in the office of the clerk of the Superior Court of Forsyth County.”

J. T. Perhins for Morgwnton Manufacturing and Trading Company.

Watson, Buxton & Watson and L. M. Swinlc for other creditors.

F. P. IJobgood, Jr., for Maryland Casualty Company.

AlleN, J:

The contract entered into between the defendants Anderson and Crews, and the bond executed by the Maryland Casualty Company to secure its performance, must be considered together, as contended by the creditors, in order to properly determine the extent of the obligations of the bond; and when we examine the contract, we find first an agreement upon the part .of the contractor to provide all the materials and to perform all the work necessary to erect the building.

The contention of the creditors is that this is an agreement to furnish the materials and labor and impliedly to pay for them, and as the .bond was executed to secure performance of the contract, the Casualty Company, is bound for th'e payment of the claim for materials.

If this is a proper construction of the contract, and the Casualty Company is bound for obligations not expressed in the bond, the conclusion contended for would seem to follow, in the absence of restrictive words in the bond; but we are of opinion this is not a correct view of the agreement of the parties.

The stipulation that the contractor will furnish the materials and labor adds nothing to the agreement to build the house, because it could not be built without the materials and labor, *290ami there can be no implied promise to pay between the contractor and the owner, the parties to the contract, as the contractor was to furnish the materials, and consequently there could be no implied promise to pay him for them, and the owner made the express promisé to pay $4,600 for the building, which included materials.

The parties undertook to reduce their agreement to writing, and presumably inserted every provision regarded material, and' it is a well recognized principle that there can be no implied contract where there is an express contract between the parties in reference to the same subject-matter. 9 Cyc., 242; Lawrence v. Hester, 93 N. C., 79.

The other part of the contract relied on simply protects the owner against liens upon his property, and against amounts he may be compelled to pay, and cannot extend the liability of the Casualty Company upon its obligation to see that the contract is faithfully performed beyond the amount for which the owner is liable.

If, however, this position was doubtful, the terms of the bond put the matter at rest.

It is therein expressly provided that, “The surety shall not be liable under this bond to any one except the owner,” and that in estimating his damages, .only those claims of mechanics and material men “paid by him” shall be included.

We therefore conclude, as it is not contended that the owner has paid any of the material men, and as he makes no claim against the Casualty Company, that his Honor properly held that the Casualty Company was not liable to the creditors.

The cases from North Carolina principally relied on by the creditors in support of their contention (Gastonia v. Engineering Co., 131 N. C., 363; Voorhees v. Porter, 134 N. C., 591; Supply Co. v. Lumber Co., 160 N. C., 428) are easily distinguishable from the one before us.

In the Gastonia case the reasonable intendment to pay grows out of the provision in the contract “for the payment of all material used and wages of all laborers employed by said contractor.” These words occur .in the contract, and there was *291nothing in the bond to indicate that the bond did not guarantee such payment. The ease also involved conditions which made it impossible for material men and laborers to protect themselves by filing liens, for the reason that the property belonged to a municipality and was not subject to liens.

In the Voorhees case the purchaser of goods expressly agreed to pay the debts of the seller, and it was held that one who guaranteed the performance of the contract to pay was liable to a creditor.

The Supply Company case was tried on demurrer. The demurrer necessarily admitted the truth of the allegation in the complaint, that the contractor agreed to pay for the material and labor, and that the bond simply guaranteed such payment. The bond contained neither restriction nor condition. It merely provided that, if the contractor should perform his contract it should be null and void, and that otherwise it should remain in full force and effect. If the contractor agreed to pay for material and labor, and the bond guaranteed that he would do so,' it necessarily followed that there was a breach of the condition of the bond when he failed to do so, and the court could not do otherwise than declare that by reasonable intendment the bond in that case was made for the benefit and in the interest of material men and laborers. There was no suggestion in it that liability under it was confined to the owner.

In all these cases there was an express promise to pay in the contract, and- a bond without restrictions to secure performance, while in the case under consideration there is no express promise, and the right to recover on the bond is limited to the owner.

This brings us to the exception of the Morganton Manufacturing and Trading Company to the ruling of his Honor, that the funds in the hands of the owner, being the balance due the contractor, shall be distributed pro rata among the claims of the material men, and not according to priority in filing the notice of liens with the clerk.

The controversy arises because of the apparent conflict between section 2023 of the Revisal and section 2035, both being parts of the same chapter, the first section providing that, “It *292shall be the duty of the owner to distribute the amount (remaining due the contractor) pro rata among the several-claimants,” and the second that, “The liens created and established by this chapter shall be paid and settled according to the priority of the notice of lien filed with the justice or the clerk.”

"When- laws have been codified, it is' permissible to examine the original legislation as an aid to correct interpretation (Rodgers v. Bell, 156 N. C., 386), and a brief history of the lien laws, enacted to secure the payment of claims for labor done and materials furnished, now collected in chapter 48 of the Revisal,’ will furnish light in the solution of the question.

The first of these in chapter 117, Laws 1868-69, which, with some enlargement, is now section 2016 of the Revisal and the succeeding sections regulating the filing and the-enforcement of the lien. Section 2035 of the Revisal was a part of this statute.

Soon after its enactment, it was held by the Supreme Court that no right to a lien was conferred by the statute unless there was a contract, express or implied, with the owner, creating the relation of creditor and debtor (Wilkie v. Bray, 71 N. C., 205), and as a result, subcontractors were excluded from its benefits, because they had no express contract with the owner, and none could be implied from the use of the materials as they were furnished- to the contractor, and under the express contract between him and the owner.

The next. step was the act to give subcontractors a lien (ch. 44, Special Session of 1880), which, with the act amenda-tory 'thereof (ch. 67, Laws 1887), is now sections 2019 to 2023, inclusive, of the Revisal, and it is in this last act of 1887 that we find for the first time the provision requiring the distribution pro rata among the subcontractors of the amount .due the contractor, in the hands of the owner at the time he receives notice of their claims, which is now incorporated in section 2023 of the Revisal.

An instructive case discussing these statutes is Lester v. Houston, 101 N. C., 609, in which the Court says:

“The Constitution requires-the General Assembly to ‘provide by proper legislation for giving to mechanics and laborers an *293adequate'lien on tlie subject-matter of their labor.’ Art. XLY, p. 4. And the statute gives the lien Tor the payment of all debts contracted for work done on the same' or material furnished.’ The Code, p. 1781., In the construction of this section, it is declared, in Wilkie v. Bray, 71 N. C., 205, that ‘in order to create the lien, the circumstances must be such as first to create the relation of debtor and creditor, and then it is for the debt that he has the lien.’
“The effect of this ruling, which makes the statutory lien an incident to and the offspring of the’ contract out of which the indebtedness springs, and confines it to the party to the contract, made at June Term, 1874, was followed by the enactment of 29 March, 1880, entitled ‘An act to give subcontractors, laborers, and material men'a lien for their just dues,’ the provisions of which constitute sections 1801, 1802, and 1803 of The Code in chapter 41.
• “It was not intended to supersede the lien of the contractor, for it in direct terms gives the lien in favor of subcontractors, laborers, and material men a preference, Hhe mechanics’ lien now provided by law,’ and provides that when notice is given, the aggregate of such liens shall not exceed the amount then due the original contractor.
“The legislation is intended to extend the remedy to those who work or furnish materials from which the owner derives a benefit in the improvement of his property, even where there are no contract relations between them and the owner, and enable them to secure, in order to the payment of what is due them, the indebtedness due from the debtor to the contractor.”

If, therefore, there was no codification of the statutes', there could be no conflict between the provision as to priorities contained in the acts of 1868-69 and relating to materials furnished under contracts with the' owner, express or implied, and the requirement'of the act of 1887, that.the balance in the hands of the owner shall be distributed pro rata among the subcontractors when there is no contract with the owner, because contained in different statutes, and applicable to different classes and conditions.

*294If so, does tbe incorporation -of tbe two statutes into chapter 48 of tbe Eevisal as one statute bring about a conflict, and are tbe two sections of tbe Revisal irreconcilable ?

It is evident tbat neither tbe commissioners wbo codified tbe statutes nor tbe members-of tbe General Assembly, wbo adopted tbeir work thought there was any conflict, as otherwise one of tbe sections would have been omitted from tbe Revisal; and it is our duty to give effect to both sections, if it can be done by any fair and reasonable interpretation. Rodgers v. Bell, supra.

When we turn to tbe chapters on liens we find tbat it has nine subdivisions, tbe second being devoted to subcontractors, and tbe . section as to priorities being in tbe sixth.

Tbe lien of tbe subcontractor is acquired by notice to tbe .owner (Rev., sec. 2020), and there is not only no requirement tbat be shall file notice of lien with a justice or a clerk, but it is expressly provided in section 2022 tbat the sums due for furnishing materials, etc., shall be a lien “without any lien being filed before a justice of tbe peace qr tbe Superior Court,” and in tbe succeeding section (2023) tbat: “In tbe event tbe amount due tbe contractor by the owner shall be insufficient to pay in full the laborer, mechanic, or artisan for bis labor, and tbe person furnishing materials for materials furnished, it shall be tbe duty of tbe owner to distribute tbe amount pro rata among tbe several claimants, as shown by tbe itemized statement furnished tbe owner.”

Tbe section relied on by tbe Morganton Manufacturing Company (sec. 2005) purports to deal with “tbe liens created and established by this chapter,” it is true; but it says, also, tbat they shall be paid “according to tbe priority of tbe notice of tbe lien filed with tbe justice or tbe clerk,” and as tbe provisions in favor of subcontractors are segregated, giving tbe means of acquiring tbe lien and of enforcing it, and have no reference to filing a lien with a justice or a clerk, except when -it says it is not necessary to do' so, we are of opinion tbat tbe two sections are not in conflict, and tbat section 2035 relates to liens required to be filed with tbe proper officers, and does not affect tbe provisions as to subcontractors, wbo acquire a lien by notice to tbe owner.

*295This is not only in accordance witb law, but also with, justice and equity, for wben men have put their money and labor in a building, and the balance due is insufficient to pay all, it is not right for one to have the whole fund, in the absence of negligence, because he gets to the clerk’s office first.

We find no error.

Affirmed.