after stating the case: It seems to us that the presiding Judge correctly interpreted the agreement between Barges and Ethridge. The parties evidently intended that Ethridge should begin the cutting and removal of the timber within the first four years, and the additional two years was granted, not as an original period for the cutting and removal, but for the purpose of enabling Ethridge to complete the cutting and removal commenced during the four years, provided *161it should be found that it was not sufficient time for cutting and removing all the timber from tbe land which is described in the complaint. Surely it was not the intention of the parties that Ethridge should'lie by and not cut a tree during the four years and then claim the right to cut and remove the timber during the two supplementary years. They were allowed, as we have said, for the purpose of completing the cutting and removal, and not as additional time to provide against the delay and laches of Ethridge in performing the work. The plaintiffs’ construction of the contract is utterly inadmissible. Our opinion, therefore, is that Ethridge should have begun cutting and removing the timber within the four years, and if, in the exercise of reasonable diligence, he was not able to finish during said period, then it is provided that he shall have the additional time, not exceeding two years, to complete the work. It was admitted that Ethridge did not attempt to cut or remove a single tree during the four years first allotted to him. Would it not be a perversion of the terms of the contract to permit him to take advantage of his neglect and to use any part of the two years to cut and remove the timber, which were merely intended to supplement the four years to the extent that further time was needed to do what could not be done within that period ? The stipulation is, not that if another full term is required to begin and finish the work, but if longer time is required for that purpose. This necessarily implies that at least some of the cutting and removing should be done during the first-mentioned period. The plaintiffs cited in support of their position the cases of Hawkins v. Lumber Co., 139 N. C., 160; Lumber Co. v. Corey, 140 N. C., 462; Mining Co. v. Cotton Mills, 143 N. C., 307; Woody v. Timber Co., 141 N. C., 471. Those cases are not in point. They relate altogether to a different question from the one presented in this case. Bunch v. Lumber Co., 134 N. C., 116, is also referred to in the plaintiffs’ brief; but that case, as well as Hawkins v. Lumber Co., decides that the party 146-11 *162wbo bas by a contract been given permission to cut and re-1 move timber must proceed to do so .with reasonable diligence, where no time is fixed. And so in this case it was not contemplated that Ethridge should waste the whole period of four years by idleness or inaction and claim the right to cut and remove the timber during the time limited for finishing the work. If we give such a meaning to the contract it will contravene the plainly expressed will of the parties, and it cannot be warranted by any recognized rule of construction. If we should so decide, both the spirit and the letter of the agreement would be violated. The law does not permit a party to sleep upon his rights. lie must be diligent.
The case of Lumber Co. v. Cedar Co., 142 N. C., 411, also cited, has no application to ‘the facts stated in the record. That decision was based upon the' statute which requires a bond to be given by the defendant in certain cases if an injunction is refused. But why do the vain thing of requiring a bond in this case, when it is apparent that the plaintiff must eventually fail in its suit ?
The ruling of Iiis Honor in refusing to continue the injunction to the final hearing, being right, is affirmed.
No Error.