Gund-Graham Co. v. State, 7 Ill. Ct. Cl. 39 (1931)

Dec. 8, 1931 · Illinois Court of Claims · No. 1850
7 Ill. Ct. Cl. 39

(No. 1850 —

Gund-Graham Company, Claimant, vs. State of Illinois, Respondent.

Opinion filed December 8, 1931.

Gund-Graham Company, pro se.

Oscar E. Carlstrom, Attorney General; Carl I. Dietz, Assistant Attorney General, for respondent.

Mr. Justice Bob

delivered the opinion of the court:

This is a suit brought by the claimant, Gund-Graham Company, a corporation, of the City of Freeport, County of Cook, State of Illinois, against the defendant, State of Illinois, to recover damages caused by the cancellation of road construction contracts No. 4531, 4540, 4541 and 4542 on State Bond Issue Boute No. 47, Section 106, awarded on the 4th day of September, 1931, and Boute No. 85, Sections 102, 102-X, and 103-X awarded on the 12th day of September, 1931.

The facts in this case are as follows: That after the complainant commenced performance under the said contracts it received a notice from the respondent on the 6th day of October, 1931, through its Division of Highways, Department of Public Works and Buildings, that no payments could be made for work done under the contracts for the reason that the “Prevailing Wage Law” under which the contracts had been let was held to be invalid and void by the courts of this State and that in the event the claimant proceeded further under the said contracts, it did so at its own peril. When this notice *40was received the complainant had already completed work under the contracts costing $8,090.69 and thereafter complainant’s forces and machinery remained idle from October 6 to November 2nd, 1931, thereby necessitating considerable expense in addition to the cost of work completed, for which the claimant asked damages, and the State was then and there so notified.

Thereupon, the Division of Highways, Department of Public Works and Buildings, of the State of Illinois, through its Director and Chief Highway Engineer, after making deductions for cement sacks salvaged, reached an agreement in settlement of the damages caused as aforesaid and stipulated to make payment in the sum of $19,082.60. The Attorney General has approved of the said settlement and stipulation; but the Division of Highways, could not pay the claim and therefore recommended that a claim be filed with this court.

As there is no dispute as to the facts presented in the claimant’s declaration,'and the evidence establishes the-claimant’s right of action, the court is of the opinion that the claim is reasonable and should be paid. The court accordingly awards the claimant the sum of $19,082.60.