Resource Technology Corp. v. Illinois Commerce Commission, 354 Ill. App. 3d 895 (2004)

Dec. 28, 2004 · Illinois Appellate Court · No. 1-04-0188
354 Ill. App. 3d 895

RESOURCE TECHNOLOGY CORPORATION, Plaintiff-Appellant, v. ILLINOIS COMMERCE COMMISSION, Defendant-Appellee.

First District (2nd Division)

No. 1—04—0188

Opinion filed December 28, 2004.

Rehearing denied February 2, 2005.

*896C. Philip Curley, Alan R. Dolinko, and Carl Bergetz, all of Robinson, Curley & Clayton, PC., of Chicago, for appellant.

John P Kelliher, Special Assistant Attorney General, of Chicago, for appellee.

JUSTICE HALL

delivered the opinion of the court:

Resource Technology Corporation (RTC) is a Delaware corporation *897that presently owns and operates approximately 15 electric generating facilities in Illinois, including the facility located at 14732 East 2100 North Road, Pontiac, Illinois (Pontiac Facility). All of the electric generating facilities, including the Pontiac Facility, are primarily fueled by landfill-generated methane gas.

RTC appeals from the judgment of the trial court granting the Illinois Commerce Commission’s (Commission) motion to dismiss RTC’s complaint for declaratory and injunctive relief and denying RTC’s motion for summary judgment on its request for the declaratory ruling.

On appeal, RTC contends that: (1) the Commission’s proposed review of the Pontiac Facility’s status as a “qualified solid waste energy facility” (QSWEF) pursuant to section 8—403.1(b) of the Illinois Public Utilities Act, commonly referred to as the “Retail Rate Law” (220 ILCS 5/8—403.1(b) (West 2000)), is preempted by the Public Utility Regulatory Policies Act of 1978 (PURPA) (16 U.S.C. § 824a—3 (2000)); (2) a facility’s status as a QSWEF under state law is automatically established when the facility files a Federal Energy Regulatory Commission (FERC) certification as a “qualified facility” (QF) pursuant to PURPA or a notice of application for such certification; and (3) the trial court erred by relying on the statutory phrase “possesses characteristics,” contained in section 8—403.1(b) of the Retail Rate Law, in finding that the Commission possessed the authority to reevaluate the Pontiac Facility’s fuel usage rate as it related to the facility’s status as a QSWEF. For the reasons that follow, we affirm.

BACKGROUND

On July 1, 1996, all of RTC’s then proposed facilities, including the Pontiac Facility, were certified as a QF pursuant to PURPA.1 Thereafter, in early 1997, RTC filed verified petitions with the Com*898mission requesting that the proposed facilities, including the Pontiac Facility, be certified under state law as QSWEFs pursuant to section 8—403.1(b) of the Retail Rate Law (220 ILCS 5/8—403.1(b) (West 2000)).2 See Resource Technology Corp., Ill. Comm. Comm’n Nos. 97—*8990031 to 97—0045 cons. (October 8, 1997). On October 8, 1997, the Commission determined that each of the proposed facilities met the requirements of a QSWEF under the Retail Rate Law, thereby entitling the facilities to receive a “retail rate.” See Resource Technology Corp. v. Commonwealth Edison Co., 343 Ill. App. 3d 36, 38-40, 795 N.E.2d 936 (2003).

On July 10, 2002, the Commission issued a citation order to initiate proceedings against RTC to determine whether the Pontiac Facility continued to meet the criteria necessary to remain a QSWEF. Illinois Commerce Comm’n v. Resource Technology Corp., Ill. Comm. Comm’n No. 02—0461 (July 10, 2002). The citation order was prompted by a Commission staff report alleging that the Pontiac Facility no longer qualified as a QSWEF because of three violations: it was operating over its configured capacity of 10 megawatts; it was using fossil fuel (natural gas) as its primary fuel rather than landfill-generated methane gas; and it had failed to file biannual and annual reports for years 1998 to 2001.

In response to the Commission’s citation order, RTC filed a complaint for declaratory and injunctive relief seeking to enjoin the Commission’s proceedings on the ground that the Commission’s action was preempted by PURPA and federal regulations promulgated thereunder by FERC. Specifically, RTC claimed that the Commission was invading the exclusive jurisdiction of FERC by attempting to determine if the Pontiac Facility was entitled to remain certified as a QF under PURPA. RTC also sought a declaratory ruling on the preemption issue and summary judgment on its request for the declaratory ruling.

After hearing arguments from both sides and considering the presented briefs, the trial court granted the Commission’s motion to dismiss the complaint and denied RTC’s motion for summary judgment. In arriving at its decision, the trial court stated that the “main issue raised is whether the Commission has the authority, as a matter of law, to make its own determination that facilities such as Pontiac meet and maintain the criteria of QSWEFs independent of any determination of concurrent federal certification.” The trial court reasoned that even though section 8—403.1(b) of the Retail Rate Law required a facility to, among other things, “possess characteristics” necessary to qualify as a QF under federal law before it could qualify as a QSWEF under state law,3 this requirement did not invade the federal jurisdiction of FERC because the statute did not give the Cont-*900mission the power to certify or decertify a facility as a QF under federal law.

The trial court determined that section 8—403.1(b) of the Retail Rate Law was not preempted by PURPA but, rather, was intended to work within the framework of PURPA. RTC now appeals from the trial court’s decision.

ANALYSIS

RTC first contends that the Commission’s proposed proceeding to review whether the Pontiac Facility is in violation of FERC fuel usage regulations {i.e., whether the facility was using natural gas as its primary fuel rather than landfill-generated methane gas) is preempted by PURPA and federal regulations promulgated thereunder by FERC. Specifically, RTC claims that the Commission’s review of the Pontiac Facility’s QSWEF status based on alleged violation of FERC fuel usage regulations is preempted by PURPA because it would invade FERC’s exclusive jurisdiction to determine a QF’s fuel usage rate.4 We must reject RTC’s contentions.

Pursuant to the supremacy clause of the United States Constitution (U.S. Const., art. VI, cl. 2), Congress has the authority to preempt state law. English v. General Electric Co., 496 U.S. 72, 78-79, 110 L. Ed. 2d 65, 74-75, 110 S. Ct. 2270, 2275 (1990). In determining whether Congress has preempted state law, a reviewing court’s task is to discern congressional intent. English, 496 U.S. at 78-79, 110 L. Ed. 2d at 74, 110 S. Ct. at 2275. This analysis begins with the assumption that Congress did not intend to displace state law. Maryland v. Louisiana, 451 U.S. 725, 746, 68 L. Ed. 2d 576, 595, 101 S. Ct. 2114, 2129 (1981). The question of whether a federal enactment preempts a state statute is a question of law subject to de novo review. Cress v. *901 Recreation Services, Inc., 341 Ill. App. 3d 149, 173, 795 N.E.2d 817 (2003).

Under the supremacy clause, a federal enactment can preempt a state statute in three circumstances. First, Congress can expressly state an intent to preempt state law (express preemption); second, intent to preempt may be reasonably inferred where federal regulation is so comprehensive that there is no room for supplementary state regulation or because the field is one in which the federal interest is so dominant that it displaces state regulation on the same subject (implied or field preemption); and third, state law is preempted to the extent that it actually conflicts with federal law (conflict preemption). English, 496 U.S. at 78-79, 110 L. Ed. 2d at 74-75, 110 S. Ct. at 2275; Schneidewind v. ANR Pipeline Co., 485 U.S. 293, 299-300, 99 L. Ed. 2d 316, 325, 108 S. Ct. 1145, 1150 (1988). Conflict preemption may occur where it is impossible for a private party to comply with both state and federal requirements or where the state regulation stands as an obstacle to fully achieving the federal objective. English, 496 U.S. at 79, 110 L. Ed. 2d at 74-75, 110 S. Ct. at 2275; Schneidewind, 485 U.S. at 300, 99 L. Ed. 2d at 325, 108 S. Ct. at 1150.

In the instant case, RTC asserts that the Commission’s proposal to review the Pontiac Facility’s QSWEF status based on alleged violation of FERC fuel usage regulations is preempted on conflict-preemption principles. RTC contends that if the Commission is allowed to conduct such a review, it would undermine the policy and purposes of PURPA by invading FERC’s exclusive jurisdiction to determine a facility’s QF status as it relates to federal fuel usage rates. RTC’s contention is meritless.

There is no conflict between FERC’s use of the federal fuel usage regulation in assessing the Pontiac Facility’s status as a QF under federal law and the Commission’s utilization of the same regulation in determining whether the facility should remain certified as a QSWEF under state law. In the event the Pontiac Facility’s QSWEF status is revoked under the Retail Rate Law and it is no longer eligible to receive a state-subsidized “retail rate,” this determination would not interfere with the facility’s designation as a QF under PURPA and would not affect the facility’s right to continue receiving federal benefits in the form of “avoided cost rates.”

The Commission is not attempting to determine whether the Pontiac Facility’s fuel usage rate complies with federal law as it relates to the facility’s status as a QF under PURPA. Rather, the Commission is attempting to determine, inter alia, whether the Pontiac Facility violated federal fuel usage rates, and if so, whether this violation prevents the facility from being recertified as a QSWEF under the *902State’s Retail Rate Law. In this regard, the Commission’s review does not stand as an obstacle to the accomplishment and execution of FERC’s objectives under PURPA. Indeed, the Commission’s proposed review furthers the federal objective of ensuring that certified facilities have a primary fuel source which is 75% biomass (¿.e., non-fossil-fuel organic matter), waste, renewable resources (e.g., wind, solar or hydropower), geothermal resources, or a combination thereof. See 18 C.F.R. § 292.204(b)(l)(i) (2004). RTC has not carried its burden of establishing that the Commission’s proposed review is preempted by federal law.

RTC next contends that the statutory definition of “Qualified Solid Waste Energy Facility” (QSWEF), as set forth in the definitions section of the Illinois Administrative Code (Illinois Code) (83 Ill. Adm. Code § 445.20 (2003)), indicates that a facility’s status as a QSWEF is “unequivocally” established when the facility files a valid FERC QF-certification with the Commission. RTC claims that once a facility obtains a valid, FERC-issued QF-certification and afterwards files that QF-certification with the Commission and becomes certified as a QSWEF under the Illinois Code, any subsequent attempts by the Commission to reevaluate the facility’s QSWEF status on alleged violations of federal fuel usage regulations runs afoul of the Commission’s own regulations, since under the regulations a facility’s status as a QF under FERC automatically establishes its status as a QSWEF under state law. In addition, RTC maintains that nothing in the Commission’s regulations allows or contemplates the Commission addressing the issue of FERC fuel usage regulations in reevaluating a facility’s QSWEF status. Again, we must reject RTC’s contentions.

Section 445.20 of Title 83 of the Illinois Code defines a QSWEF in relevant part as follows:

“ ‘Qualified Solid Waste Energy Facility’ (QSWEF) means a facility that meets the criteria set forth in 18 CFR 2925 ***, and the Local Solid Waste Disposal Act ***, or an electric generating facility which uses methane gas generated from landfills and meets such requirements of 18 CFR 292.” 83 Ill. Adm. Code § 445.20 (2003).

In turn, section 445.30 of Title 83 of the Illinois Code, entitled “Availability of Benefits,” states in relevant part as follows:

“a) The benefits of this Part shall apply to any qualified solid waste energy facility. The owner(s) or operator of such a facility

*903RTC argues that pursuant to section 445.30(b) of the Illinois Code, a facility can establish itself as a QSWEF simply by filing either a FERC-issued QF-certification with the Commission or a notice of application for such certification. The problem with RTC’s argument is that pursuant to section 445.30(a) of the Illinois Code, in order for a facility to receive state benefits under the Illinois statute, the facility must not only comply with 18 C.F.R. 292, it must also meet the requirements and criteria specified in the Illinois Public Utilities Act, which includes the Retail Rate Law.

Under section 8 — 403.1(b) of the Retail Rate Law, a QSWEF is defined as a facility that the Commission determines qualifies as a qualified solid waste energy facility under the Local Solid Waste Disposal Act; uses methane gas generated from landfills as its primary fuel; and possesses characteristics that enable it to qualify as a cogeneration or small power production facility under federal law. 220 ILCS 5/8 — 403.1(b) (West 2000).

Pursuant to the Illinois Public Utilities Act, the Commission has the authority to determine whether the Pontiac Facility’s violation of federal fuel usage rates prevent the facility from being recertified as a QSWEF under the State’s Retail Rate Law. See, e.g., Continental Mobile Telephone Co. v. Illinois Commerce Comm’n, 269 Ill. App. 3d 161, 167, 645 N.E.2d 516 (1994) (Commission derives its authority from the Illinois Public Utilities Act); Local 777 v. Illinois Commerce Comm’n, 45 Ill. 2d 527, 535, 260 N.E.2d 225 (1970) (Commission regulates all public utilities pursuant to the Illinois Public Utilities Act).

In sum, a facility’s status as a QSWEF is not automatically established merely because the facility files a FERC QF certification *904with the Commission or a notice of application for such certification. In addition, even after a facility is certified as a QSWEF, the Commission has the authority under the Illinois Public Utilities Act to reevaluate whether the facility has continued to satisfy the requirements necessary to retain its status as a QSWEF.

Finally, RTC asserts that the trial court erred by relying on the statutory phrase “possesses characteristics,” contained in section 8 — 403.1(b) of the Retail Rate Law, in finding that the Commission had the authority to reassess the Pontiac Facility’s fuel usage rate. We must reject RTC’s argument.

In granting the Commission’s motion to dismiss the complaint and denying RTC’s motion for summary judgment, the trial court reasoned that even though section 8 — 403.1(b) of the Retail Rate Law required a facility to “possess characteristics” necessary to qualify as a QF under federal law before it could qualify as a QSWEF under state law, this requirement did not invade the federal jurisdiction of FERC because the Illinois statute did not give the Commission the power to certify or decertify a facility as a QF under federal law. As set forth above, the trial court’s analysis in this regard was correct. The trial court did not err by utilizing the phrase “possesses characteristics” in its analysis.

Accordingly, for the reasons set forth above, the judgment of the circuit court of Cook County is affirmed.

Affirmed.

BURKE, EJ., and GARCIA, J., concur.